When a confections manufacturer needed to relocate internationally, it had to move its lines to an existing facility without interrupting operations while also consolidating and optimizing the relocated lines to reduce costs.
The engineering manager for this company knew he needed to bring on an experienced partner to perform this work and also help the organization gain operational efficiency and better meet market demand. However, this was complicated since news of the plant closure was confidential, making bidding out the project not an option.
To ensure a smooth relocation process, Polytron developed a conceptual plan that detailed the groundwork for the international move. We also performed engineering work, assessments on the existing equipment, and consolidated assets from multiple packaging lines to incorporate lines into the existing U.S. facility. By performing vendor management, we also helped resolve ingredient delivery issues, facilitate a near vertical startup, improve efficiencies in the new line, and reduce startup time by approximately 25 percent, resulting in a successful relocation process.
Challenge |
|
|
Solution |
|
|
Results |
|
Relocation and consolidation of factory lines across international borders without internal staff support.
|
Developing a flexible, detailed moving plan that anticipated possible challenges Performing an engineering study to determine if/how relocated equipment should function in the U.S. plant Resolving ingredient delivery issues from the previous plant Facilitating construction required to consolidate lines, including development of a master plan and vendor management |
Achieved a near vertical startup in the new location Improved efficiencies achieved in new lines Freed up the engineering manager to focus on his job because of his trust in Polytron Demonstrated confidence and certainty of outcome |
To better meet market demand and gain operational efficiency, a confections manufacturer concluded it needed to close its Canadian facility and move its lines to an existing factory in the U.S.
The senior regional engineering manager was responsible for the move – a $28 million project – and faced substantial challenges without internal staff support, including:
The engineering manager knew he would need an experienced partner to pull this off, but with news of the closure being kept confidential, bidding the project out wasn’t an option. Fortunately, he had engaged Polytron for project management before and trusted our expertise and ability to work within the constraints the confidential project imposed.
With a move this involved, a detailed plan is a make-or-break proposition. The engineering manager needed to conduct a situation analysis that could diminish uncertainty and develop a program to deliver the project within the deadline and budget required.
Our flexible project delivery model anticipates challenges and allows wiggle room for unanticipated events that can throw complex projects off target. By completing front-end engineering (FEE), we provided the engineering manager with options and recommendations for fitting the relocated equipment in the U.S. plant while optimizing cost. The FEE study also helped facilitate making the best decisions for the business.
After the FEE, the engineering manager had the situation analysis and recommendations he needed to move forward. Since we have extensive experience delivering these types of projects, he saved months previously needed to negotiate with another provider to execute the plan. At this point, the engineering manager could confidently turn the project over to our team and focus his energy on building an engineering team internally to take on future business initiatives and market demands.
We worked onsite in both the Canadian and U.S. plants to lay the groundwork for a successful move, which included:
The relocation plan included a program for the construction necessary to incorporate the former Canadian lines into the U.S. plant. Our team was responsible for a variety of mechanical and process engineering tasks to make this happen including:
To help the engineering manager minimize impact on the U.S. plant during the relocation, our team:
As part of the move, the engineering manager wanted to resolve ingredient delivery issues. We helped achieve this objective by working with plant personnel and process vendors. Vendor management services ensured equipment specifications were met, including implementation of safety features required for the Canadian equipment to be compliant with U.S. regulations.
Vendor management also helped the engineering manager facilitate a near vertical startup. As part of combining the Canadian and U.S. lines, we modeled a new batch deck that included four mixers, liquid ingredients, dry ingredients, manual adds, and discharge conveyors.
Using PolySimsm, a proprietary modeling and emulation tool, the team pre-tested PLC programs and HMI applications, getting everyone – including vendors – on the same page and reducing startup time by approximately 25 percent.
From front-end-engineering through full execution, Polytron worked with the engineering manager to meet the manufacturer’s production strategy. With this support, the engineering manager could maximize production inside the landlocked U.S. facility, saving the expense of expanding the plant. At the same time, with our team managing all aspects of the relocation, the engineering manager could lead his engineering team in planning the manufacturer’s next expansion.
Ultimately, our conceptual planning enabled a big picture perspective – a five-to-ten-year vision for production at a number of sites, which included everything from actual execution of each project to delivering the overall business plan.
Mechanical EngineeringSystem-focused mechanical engineering to support manufacturers in equipment layout, integration, optimization, and installation. |