A beverage manufacturer was experiencing unexpected production losses, but the source of the problem was still unknown. Communication disruptions between factory floor assets would prompt system shutdowns causing time-consuming repairs.
Equipment and communication networks were failing due to the network’s aging infrastructure. Outdated wiring and Ethernet was threatening the plant’s overall production efficiency – putting the business at risk!
A new copper and fiber network was installed in parallel to the existing network allowing for a seamless migration and uninterrupted line production. The updated network provides the desired performance results and delivers a secure, sustainable, and scalable system that eliminates production downtime issues.
Challenge |
|
|
Solution |
|
|
Results |
|
Update industrial network to fix communication disruptions between factory floor assets while plant is in full production.
|
Select a partner to evaluate and design a network to improve bandwidth utilization efficiency across all manufacturing with no interruption of production. |
Reliable and expandable infrastructure was designed, configured, and installed to increase efficiency and support future growth. Network sustainability was simplified with updated standard technology, methodology, and network health diagnostics. Plant production was not interrupted. |
As unplanned production losses piled up, the operations technology manager at a global beverage manufacturer was struggling to identify the source of the problems. Intensive investigation led him to see the communication disruptions between factory floor assets. Systems would go down, necessitating time-intensive trouble-shooting and increasing everyone’s stress.
Failing equipment and communication networks, some of which were 20+ years old, proved to be the culprit. Like many plants, the network’s aging infrastructure of wiring and Ethernet had not been upgraded to serve the manufacturer’s changing needs, and it was causing timing issues. New components were continually being “bolted on” using multiple protocols, and the network was close to collapsing. To further complicate matters, there was no in-house expertise to upgrade the network.
The operations technology leader faced a common problem in today’s manufacturing environment: aging infrastructure was threatening his plant’s overall production efficiency, putting the business at stake.
The operations technology manager reached out to Polytron make the right capital investment for the health of his company. Polytron evaluated and designed a network architecture to improve overall bandwidth utilization efficiency across all manufacturing areas. The enhancement was critical to supporting future growth.
This would require a new high-performance copper and fiber system that would exceed the manufacturer’s requirements for enterprise, industrial networking, and security standards.
Polytron’s role was to:
Polytron followed its proven Roadmap to Network Solutions working through the following steps:
The operations technology leader couldn’t afford line downtime while the network was being replaced, so the team designed an implementation plan to allow uninterrupted production:
Step 1: Install and configure new fiber network of optic cabling. Validate by testing communication with plant assets before moving forward.
Step 2: Migrate all the plant’s industrial servers to the new network. This step required the most resources from plant’s IT support group. Servers were validated and stabilized.
Step 3: Migration of operational assets were then implemented from low risk to high risk. Each area was validated before moving on to the next operational area.
Step 4: With migration complete, the team conducted a Network Health Assessment connecting to the core switch and testing to check for any issues and/or communication disruptions.
Step 5: In order to reduce migration risk because of old, dated medium, the project team installed all new copper and fiber in parallel to the existing network.
This parallel installation allowed the project team to reduce installation risk, continue with day-today operations and have a seamless migration transition.
Polytron enabled the operations team by delivering a streamlined training protocol to each operations support group as identified by the Project Roadmap. As one area was validated and running smoothly, hands-on training and hand-off was conducted before moving on the next area.
The updated network provides the desired performance results and delivers a system that is secure, sustainable, and scalable. Polytron’s experience and expertise has allowed the operations technology manager to eliminate costly and stressful network-related production downtime across the plant line. The updated network also increased the plant’s networking support structure, ease of maintenance, and introduced new technologies that can be used in future plant projects.
Industrial Network and SecurityProtect the integrity, availability, and security of all your plant floor network assets. |