Downtime, reduced productivity, and poor product quality raised the risk that a food and consumer goods packaging manufacturer could not meet customer needs and demand.
End-of-life drives, unsupported controllers, and obsolete variable frequency drives (VFDs) were causing hours of downtime per week on the winder equipment creating poor product quality.
The extruder, webbing, and winding section of production was updated and optimized to resolve the obsolete components on the process side of the line. To abide by the manufacturer’s budgetary planning requirements, Polytron plotted a strategy that prioritized the most problematic components for replacement and captured those that could be postponed. Control system errors were eliminated, new technology is supported by many vendors, and line capacity increased resulting in the ability to meet customer demand.
Challenge |
|
|
Solution |
|
|
Results |
|
Obsolete equipment and related systems caused downtime that risked the company’s ability to serve customers. |
Update and optimize extruder, webbing, and winding section of production line and resolve obsolete components on the process side of the line. The work was done in two phases to minimize the problem quickly while also accommodating budgetary constraints.
|
Control system errors entirely eliminated Capacity available to reliably serve customers in the short and long term Widely used technology is implemented that can be supported by many vendors |
Its end-of-life drives and controllers often caused hours of downtime per week. Old proprietary PLC controllers were no longer supported by the OEM and spare parts were no longer available on the market. With the controllers reaching end-of-life, support resources had diminished until only one person knew how to keep the production lines running.
The manufacturer’s variable frequency drives (VFDs) were also obsolete and no longer supported.
Poor product quality and frustration across the plant floor compounded the stress. Though it would be a substantial undertaking, the company’s director of engineering knew the situation had to be addressed.
After identifying goals, the engineering director brought Polytron on as a consultative partner to support the technology, process and organizational changes required for success. Working with other contractors, Polytron supported restoration of the facility by executing a number of engineering projects, including:
The team determined that a complete update of the line would exceed the manufacturer’s budgetary planning requirements. Polytron plotted a strategy that prioritized the most problematic components for replacement Phase 1 and captured those that could be postponed to Phase 2:
Phase 1: Update and optimize the extruder, webbing, and winding section of the production line which controls pressure and blending.
Phase 2: Resolve the process side of the line which manages winder and die temperatures.
This section of the production line included multiple proprietary programming and several variations of drives with different vendor protocols. To ensure the work satisfied project goals and delays were avoided, Polytron conducted a thorough audit to ensure all details were addressed for the scope of work.
Unforeseen issues arose during the project, including:
In the end, total execution time for Phase 1 was only six to eight weeks. Polytron executed shutdown and startup over the Christmas holiday, allowing the manufacturer to minimize production impact.
Preparing to execute Phase 2, the engineering team conducted a field audit to verify wiring and I/O as the drawings provided were not up-to-date. Collecting current info was critical to creating accurate design.
Obsolescence and ModernizationPerform strategic upgrades to improve reliability, safety, and productivity. |